Works update – 18 January 2024
Kyogle Council News 18 Jan 2024

Most of Council’s work crews are back on deck after the Christmas break and work has re-started on the upgrade of Clarence Way, and the Bruxner Highway project at Mallanganee Range.

Work has also commenced on the rehabilitation of a 3.5km section of Ettrick Road.

Council is undertaking maintenance grading on Old Cob ‘O Corn and Duck Creek roads. The grading crews will move to Capeen Creek Road and into the Cawongla catchment once that is complete.

Pothole crews are, and will be working on, Gradys Creek and Kyogle roads and Clarence Way over the next few weeks. Roadside slashing is scheduled for Clarence Way, Kyogle Road and Fawcetts Plain Road.

Flood damage repairs on the Clarence Way south of the Bruxner Highway have commenced and will continue through February.

Remediation work on the Gabal Road landslip is continuing and is expected to be completed last this month.

Work has started on the new bridge on Rodgers Road while construction continues on Askews Bridge on Askews Dip Road, Gambleys Bridge on Gambleys Road, and the new Back Creek Bridge on Kyogle Road.